1st July 2007
First Job this Month "Divert Stream at Rear of Bothy"
August Dig Foundation.
Foundations Done
September moving on to Block and Stone to DPC. Kitchen to DPC. 8th Sept. Radon Sumps.
14th Sept Bath/dressing rooms,piers,and up to DPC.
October Bothy Cats return,five kittens born in the Bothy,all doing well. Slab floors ready to pour Friday 11thOct.
Next Job!!!!!!!!
Old Roof off!!
Back soon lol l
ol
November Doorways
Kitchen and bathroom/dressing room walls.
StoneWork Starting&Trouble at mill Wagon Driver Atempting to drive onto the field in wet LOL Silly Boy.
Almost Winter Solstice the 18th Today,frost early morns brrrrrrrr.but the stone workers are still working.
1st Jan 2008
Roof Timbers and Gables.
24th January 08,Stonework nearly finished,timber rafters going on Monday,
2Feb Traditional Timber Roof complete.Slates next.
15th Feb roof done,inside now phewwwww |
Submitted by a neighbour “Do they mean me”lol Artist Impression of Rear Newlands.
The Stream is Diverted!!!! Raised from the Earth!Trilithion1
Trilithion2 Trilithion Going 



|
|